
Our Construction Site
November 2006
December first has arrived and a real lot of progress has been made during this
last month. It seemed like forever but now we can all
see
the building beginning to rise above the fence around the project. At the
beginning of November we were finishing the concrete floor in the basement area
of the new church. Now I will walk you through what has taken place since the
last I wrote this report to you. I would like to finally take this time to
introduce you to the writer and some of the players in this construction
venture. I am Bob Mainusch, member of ECC and of the construction committee. The
contractor on the job is Kamal Fouad, General Manager of Al Mahaba Cont. Other
active members of the committee are David Winning and John Lan. Each week since
the construction began each of these persons meet to go over progress and solve
upcoming problems. Even at this point in the construction phase there is a
constant review taking place to be sure that everything that was designed into
the building will end up being there and working properly. There is no time for
rest.

Now
for this month’s update. Once the floor was placed and hardened the workers
began to build the formwork for the walls. This included all the steel
reinforcement bars (rebar) that actually give the strength to the building.
Inside the walls are many, many conduits each tied into place within the steel
framework. Thousands of steel rebar are placed within the walls and floors.
While the walls and floors of the main building are being formed the new main
entrance construction was rising even faster out of the ground. The first thing
that was truly visible across the wall was that new entry and stairwell area.
This area will soon become the new entry into the church and to the upper floor
and at that time the existing stairs inside will be demolished so the new main
entrance can be completed.
The
reinforcement bar all has to be cut to size then bent into its proper shape tied
together so it will not move when the concrete is placed inside the forms. The
forms are made up of plywood which is carefully held in place and at a very
specific space. In the picture the outside of this wall has the plywood already
in place and the workers are fastening the steel rebar together to form the
inner structure of the wall. Several different sizes or conduit which looks like
pipe is then placed inside the forms and tied to the steel. These conduits will
later on have electric wires or telephone cables or TV cable or even water pipes
run through them depending on the need for that area. All these conduits have to
be carefully planned out before the second side of plywood can be fastened to
the completed form and the placement of the concrete. Many, many man-hours are
spent cutting, placing, tying and wrapping all these different parts together.
Then it is checked and rechecked and only after totally being inspected is the
concrete poured into the forms. After a couple days for the concrete to harden
the plywood forms are then removed and preparation is then made for the next
step.
The
contractor, Kamal, spends most of his days and into the evening supervising the
work that is taking place. In the picture to the right you can see all the steel
rebar that has been formed and also the scaffolding that was placed on the new
basement floor that was needed to support all the long precast concrete floor
pieces that made up the new main sanctuary floor. Those concrete slabs are what
is called “hollow core” flooring and each slab was 17 meters long and weighed
approximately 22 tonnes.
The
next picture shows one of these slabs being lowered to the scaffolding. When all
these slabs were in place on top of the scaffolding then the contractor had to
be sure that the height for each slab was exactly where it needed to be. When
that was done, more rebar was placed on the slabs and the floor of the main
sanctuary along with all the conduits for utilities. Again many hours spent
assembling and checking to be sure all was properly in place. Next was to place
the concrete. This was a single pour that formed not only the floor but also
created the exact concrete support for the concrete slabs. This assures that
everything is locked together into one solid structure. As the contractor told
me, now the real hard part is done. As I had explained earlier the basement and
all the work that took place there is so important to have done perfectly. From
here on construction should continue at a fairly fast rate.

November ended with the first real look at just how large the new main sanctuary will be. Looking into this last picture you can see the sub floor and the base for the new pulpit with its built in Baptistery. The concrete is kept wet to keep the concrete floor from cracking. This is where I wish everyone could see this personally as I have, unfortunately for safety reasons this is not possible. All I can tell you is that it is now an awesome feeling to see all this coming into being.