Building Gallery Page | ECC Home Page

  Our Construction Site

August 2006

 

Earthwork BeginsThe real construction has now finally begun. At least there are large holes in the ground and it appears like we are under way with building the new church. This portion of the construction by the contractor is extremely important because this is the beginnings of the base for the entire church. The below grade work is where everything must be done correctly in order to have a firm foundation for the new building with everything being square and level. If things are done wrong here then the whole building will have problems and pieces or rooms will just not fit together like they were designed.

 

We have all waited and watched as first the old building began being torn down. I know that over the months now I have heard many comments on “why is this all taking so long” and other questions like that. All buildings under construction need to follow the same tedious steps in order to build a good, strong structure. Any short cuts taken can and most likely will have disastrous results so everyone must practice patience.

 Water in the Basement

Site preparation of this type takes on many new challenges. The big hole in the ground. All the concrete pilings are now cured and ready for the weight load that will be placed upon them. The contractor then removes all the extra soil to lower the foundation which will make room for what will be the large multi-purpose room in the basement. All of Abu Dhabi sits very low with regard to the level of the Gulf waters so when digging out the soils began the contractor dug into the ground water below. A pumping system had to be installed to remove all that water from the new basement area so that the waterproofed footers and floor and side walls could be constructed.

 

New Stair TowerRight outside the two old exit double doors you can see wooden form work. These are the very first beginnings of what eventually will become the left-hand stair tower as you look at the artist rendering in the heading of this document. The contractor will be building this portion first so that fairly soon we can use that as our entrance into the building and it will go to both floors. Shortly after that portion is completed and ready for use some more of the existing building will be removed as construction progresses. Some of the pilings still need to be reworked but that is all what I referred to earlier about all the preliminary work that has to be done to make a good, firm foundation. Sometimes it is hard to visualize just what you are seeing. The extra lengths of steel will eventually be a part of the next pour of concrete and become part of the walls.

 

Moving a Porta-CabinSeveral modular buildings or porta-cabins have been placed on the small plot of land next to the present church on the side street. These temporary buildings will serve us for several different uses. The porta-cabin shown contains two large rooms each with its own bathroom, Among the planned uses are one room will be used for our caretaker. One room will be a classroom and other areas yet to be decided upon. Construction of the new building required a large portion of the old building to be demolished which took away a lot of our rooms and storage. We are trying our best to get back a little bit of this lost space by using these temporary buildings but we are still going to be short of space and patience by all is appreciated.

 

 Building Gallery Page | ECC Home Page